BCU-FTS-64114 - Waunfawr Integrated Hub
Betsi Cadwaladr University Health Board
- Value
- £7,200,000
- Published
- 3 Nov 2026
- Deadline
- 8 Dec 2026
- Procedure
- Open procedure
- Category
- 45000000 — Construction work
- Location
- UKL12, United Kingdom
- Notice reference
- 104389-2026
Requirements summary
Betsi Cadwaladr University Health Board is procuring a works contractor via an open procedure for the proposed Waunfawr Primary Care Centre at Fferm Cross, Gwynedd. The contract uses a two-stage JCT design and build route, with a Stage One Pre-Construction Services Agreement and a Stage Two build conditional on Employer approval. The estimated value is GBP 6.0m net (GBP 7.2m gross), with evaluation weighted 40% technical and 60% cost and commercial.
Key requirements
- Design and build contractor for new primary care accommodation, including clinical and support spaces
- Stage One PCSA services covering design development, surveys, planning, statutory approvals, utilities, risk reduction and open-book cost planning
- Stage Two maximum price and Contract Sum Analysis, proceeding only after Employer gateway approval
- Project-specific Stage One delivery strategy, including programme, healthcare planning methodology, information management and SYPRO or Employer-confirmed platform arrangements
- Capability to support a possible single-stage appointment route without reducing Employer's Requirements
- Site works including external accommodation, parking, access and utility infrastructure, plus commissioning, handover and aftercare
- Contract period from 8 February 2027 to 30 March 2029 under JCT Design and Build Contract 2024 with Project Bank Account