Closed

Berths 9-10-11 Construction, Montrose Port

Montrose Port Authority

Value
£35,000,000
Published
28 Sept 2026
Deadline
16 Oct 2026
Procedure
Restricted procedure
Location
UKM71
Notice reference
091183-2026

Requirements summary

Montrose Port Authority is procuring a contractor for the design and construction of a new quay, associated hardstanding, utilities and dredging at Berths 9-10-11 in Montrose Port, Scotland. The works are to be delivered as a design-and-build contract under NEC4 ECC Option A with an activity schedule, with an estimated value of GBP 35,000,000 and a restricted procedure with four second-stage candidates. Tender submissions are due 16 October 2026, with a contract period from 31 August 2027 to 31 August 2029.

Key requirements

  • Design and construction of a new quay structure at Berths 9-10-11, Montrose Port
  • Construction of new hardstanding areas, quay furniture and associated services and utilities
  • Associated dredging works
  • Design-and-build delivery under NEC4 ECC Option A (priced contract with activity schedule)
  • Restricted procedure with four candidates invited to second stage; award 70% cost, 30% quality
  • Staff names and qualifications required; tender due 16 October 2026; contract period 31 Aug 2027 to 31 Aug 2029