SJM2 – Contractor Procurement – Main Works

The Crown Estate

Value
£386,400,000
Published
23 Oct 2026
Deadline
Not stated
Procedure
Competitive flexible procedure
Category
45210000 — Building construction work; 45331000 — Heating, ventilation and air-conditioning installation work; 45453000 — Overhaul and refurbishment work; 45454100 — Restoration work
Location
London, UKI32, SW1Y 4AH, United Kingdom
Notice reference
100431-2026

Requirements summary

The Crown Estate is procuring main construction works for St James Market Phase 2 in London, including a new c.312,500 sq ft (NIA) CAT A office building around the retained Grade II listed Carlton Cinema, plus cinema shell and core refurbishment, retail shell and core, landscaping, public realm and new UKPN substations. The works are delivered via a Pre-Construction Services Agreement, then an amended JCT Design and Build 2024 contract, with a separate 130 Jermyn Street option. The stated total value is £322m excluding VAT (£386.4m including VAT).

Key requirements

  • Main works contractor for St James Market Phase 2 under a PCSA followed by an amended JCT Design and Build 2024 contract
  • Construct a new c.312,500 sq ft (NIA) CAT A office building (Basement Level 2 to Level 7) around the retained Grade II listed Carlton Cinema
  • Shell and core refurbishment of the Carlton Cinema, plus retail shell and core accommodation
  • Landscaping and public realm works, and new UKPN substations
  • Watching brief over, and novation of, the separate Demolition Contract
  • Optional 130 Jermyn Street works (c.£100m ex VAT) that may share an energy centre, plant and practical completion programme with SJM2
  • Contract period from 4 June 2027 to 31 January 2031, extendable to 2033; evaluation weighted 60% technical and 40% commercial
SJM2 – Contractor Procurement – Main Works — The Crown… | ProposAI